Project rooms for OTEC GmbH & Co. KG

The WERK 12, 13 and 17 in the Werksviertel-Mitte

At a glance

32,000 sqm
Rental space

>50 companies
Project participants


Challenge
Integration of all project participants such as planners, experts and executing companies, as well as data that is up-to-date.

Solution
With PAVE, all documents are up-to-date, errors are minimized and collaboration is optimized.

Requirements for PAVE

The idea of ​​innovation plays a decisive role both in the basic concept and in the execution of the project work. An important component in the overall development of the area is the effective design of the construction processes.

“The project in the Werksviertel is a great challenge for us and makes us very proud. For this, on the digital side, we need a reliable partner for the entire construction process, software for collaboration and the exchange of all data between those involved in the project”, says Funda Faust, Dipl.-Ing. architect at OTEC.

Why PMG

When asked about the advantages of PMG, Ms. Faust says<em>: “The cooperation with the digital platform of PMG supports and accompanies the project planning and implementation of the new buildings in an uncomplicated way. Based on the experience with Werk12 and Werk17, the continuation of the cooperation in our current Werk13 construction project was a matter of course.”</em>

&nbsp;

In addition, OTEC sees enormous added value in the interactive processes between all those involved in the project. Everyone has the right, up-to-date data available at all times – this saves long searches and optimizes work processes.

“Above all, the constant further development of the project room as well as the constant availability of the support, who is very well versed in technical questions and always provides support, convinced us”, said Ms. Faust

The project

With the Werksviertel-Mitte, a creative urban quarter is emerging in Munich that is constantly changing. Life, work, entertainment, art and culture merge into a unique urban togetherness in the east of Munich. The Werksviertel-Mitte offers space for great architecture as well as digital, creative and artistic innovations. Every day a lively urban culture unfolds in the quarter, which can be actively shaped and experienced over and over again. Under the motto “the diversity of the special”, those responsible at the Werksviertel-Mitte have made it their business to implement this diversity in all aspects. This extends to all areas of life that are important to create a place that offers something around the clock for all ages and budgets.

WERK12 was awarded the star of architecture from the evening newspaper and the DAM Prize 2021 (German Architecture Museum).

PAVE supports OTEC GmbH &amp; Co. KG
in these projects

Werk12

WERK12 impresses with its open design and architecture, which is inspired by the Dutch pavilion, which was designed by the MVRDV architectural office (Rotterdam).

It conveys a feeling of freedom: cascading stairs, glass facades, double the room height and the surrounding balconies with a depth of over 3 meters.

Other special features are the external access, the flexible gallery architecture with inserted cubes and the sun protection, which is also attached outside.

With tenants such as body + soul, GinCity, Audi and other companies, a colorful mix of gastronomy, adventure and business is ensured here too. The building has been in operation since May 2019.

Architects: MVRDV, Rotterdam and N-V-O Architects, Munich

Areas: 7,000 sqm of loft space for offices, fitness & entertainment

Werk13

New construction of a multifunctional commercial building with integration of the existing event hall.

Project duration: 2019-2022

Architects: N-V-O Architects, Munich

Areas: 2,000 sqm of studio and retail space and 3,500 sqm of multifunctional office space

Werk17

Hotel, trade & gastronomy.

Project duration: 2016 – 2025

Architects: Hild and K Architects, Munich and Berlin

Areas: above ground approx. 10,000 sqm / underground approx. 10,000 sqm

„The cooperation with the digital platform of PMG supports and accompanies the project planning as well as the realization of the new buildings in an uncomplicated way. Based on the experience with Werk12 and Werk17, the continuation of the cooperation in our current Werk13 construction project was a matter of course.“

Funda Faust
Dipl.-Ing. architect at OTEC GmbH & Co. KG

Other PAVE Case Studies

MAIN YARD Frankfurt a. M. ORT Group

„We have high expectations of our partners in terms of data security and data protection. PMG meets all the requirements here.“

Rafael Bossler
Projektmanager ORT Group

30 successful construction projects with PAVE

„Perfection is achieved, not when there is nothing more to add, but when there is nothing left to take away [Antoine de Saint-Exupery].”

Eric Fellmann
Head of construction project management experts at SWM GmbH

A project room for the Premier Inn Leipzig

“The biggest challenge in this project was project management. In PAVE, we had an overview of plans, schedules and costs. This way, efficiency and quality go hand in hand.”

Neset Uguzoglu

Project Manager at Premier Inn Holding GmbH